Fortuna Mining has received a notice of admissibility from Senegal’s Ministry of Mines and Geology for its Diamba Sud gold project exploitation permit application, the company announced on November 3, 2026.
The notice, received on November 2, confirms that the Ministry has completed its review of the application documentation and that the file complies with all regulatory requirements.
The company expects the government’s internal approval process for the final exploitation permit to be completed during the fourth quarter of 2026. Full-scale construction remains subject to receipt of that permit, with a formal final investment decision to follow.
Fortuna said early works are progressing to support the project schedule. The company has appointed African project management and engineering firm SENET as engineering, procurement and construction management contractor, completed front-end engineering design, and reached 15% progress on detailed processing plant engineering.
Purchase orders have been placed for critical long-lead equipment, including a semi-autogenous grinding mill, a primary crusher and carbon-in-leach tank plate work, while key construction packages have been awarded.
Manufacturing of the power station’s heavy and light fuel oil generators is under way, with the light fuel oil units having completed factory acceptance testing and been shipped. Construction of the accommodation camp is also advancing: earthworks are 80% complete, civil works 40% complete, and buried services are nearing completion. Land compensation and clearing for major infrastructure footprints are also progressing.
“Following our July final investment decision on the 30% plant expansion at our flagship Séguéla mine, and with Diamba Sud advancing through the final stages of permitting, we are progressing along a clear growth path,” said CEO and director Jorge A. Ganoza. “Together, these projects underpin our target of about 60% growth in yearly gold production to a yearly rate of 500,000 oz from mid-2028.”
The application process for Diamba Sud began in February 2026. The project is located in Senegal and is part of Fortuna’s pipeline of growth assets alongside the Séguéla mine.